Background:
Reynolds Consulting Engineers was hired to commission all of the building systems for the YorktownHigh School replacement and renovation program.
Phase I of the project consisted of the construction of a new 3-story 55,000 s.f. addition and minor renovations throughout the existing building. Phase II of the program will include extensive phased demolition of the current facility, and construction of a large addition. The final completed project will encompass 349,000s.f.
Arlington Public Schools has decided to pursue LEED Certification for the Phase II design and construction project at Yorktown High School.
Owner:
Arlington Public Schools
2770 South Taylor Street
Arlington, PA 22206
Services:
Building Commissioning for LEED certification
Project Cost:
$107.9 million