Background:
Reynolds Consulting Engineers was assigned to provide commissioning services for all of the building systems for the Penn State University Chemistry Building. This 199,000 s.f. building is highly technology intensive and, thus, has numerous challenges for commissioning. Systems included in the commissioning process were: fire protection, HVAC, plumbing, electrical and control systems.
Owner:
Pennsylvania State University
106A Physical Plant Building
University Park, PA 16802
Services:
Building commissioning
Project Cost:
$63.5 million